Application of EECA
Application of EECA 2024
- EECA shall apply to Peninsular Malaysia and Federal Territory of Labuan
Legislation Structure
- Act
- Energy Efficiency and Conservation Act (EECA) 2024 - Regulation
- Energy Efficiency and Conservation Regulation (EECR) 2024 - Guidelines
- Guideline on Ascertaining Energy Consumer
- Guideline on Function and Duties of Registered Energy Manager
- Guideline on Energy Management System
- Guideline on Energy Efficiency & Conservation Report
- Guideline on Energy Audit Report
- Guideline on Ascertaining Building and Energy Intensity Performance of the Building
- Guideline on Energy Using Product - Guides
- Guide on Registration for Energy Manager
- Guide on Registration for Energy Auditor
- Guide on Registration for Training Institutions
Obligations
Energy consumers whose energy usage equals to or exceedEnergy consumers whose energy usage equals to or exceed the prescribed energy consumption threshold of 21,600 GJ in twelve (12) consecutive months must:
Appoint a Registered Energy Manager (REM)
The appointment must be made within 3 months from the date of notice in accordance with Regulations 4, 5, and 6 of the Energy Efficiency and Conservation Regulations 2024 [P.U.(A) 466/2024].
Develop and Implement an Energy Management System (EnMS)
EnMS must be developed and implemented based on the Guidelines on EnMS issued by the Commission within 1 year from the appointment of the first REM.
Submit Energy Efficiency and Conservation (EE&C) Reports
The first report must be submitted within 30 days after the end of 1 year from the date of the first REM appointment, and subsequent reports must be submitted within 30 days after the end of each year based on the anniversary of the first REM appointment. Report must be prepared in accordance with Guidelines on EE&C Report issued by the Commission.
Conduct Energy Audit (EA) and Submit Energy Audit Report
Appoint a Registered Energy Auditor (REA) to conduct an energy audit and submit the energy audit report. The first audit report must be submitted within 1 year from the date of notice, and subsequent reports must be submitted every 5 years, or where an exemption notice is issued, in accordance with the period specified in the exemption notice. Report must be prepared in accordance with Guidelines on EA Report issued by the Commission. the prescribed energy consumption threshold of 21,600 GJ in twelve (12) consecutive months must:
-
Appoint a Registered Energy Manager (REM)
The appointment must be made within 3 months from the date of notice in accordance with Regulations 4, 5, and 6 of the Energy Efficiency and Conservation Regulations 2024 [P.U.(A) 466/2024].
-
Develop and Implement an Energy Management System (EnMS)
EnMS must be developed and implemented based on the Guidelines on EnMS issued by the Commission within 1 year from the appointment of the first REM.
-
Submit Energy Efficiency and Conservation (EE&C) Reports
The first report must be submitted within 30 days after the end of 1 year from the date of the first REM appointment, and subsequent reports must be submitted within 30 days after the end of each year based on the anniversary of the first REM appointment. Report must be prepared in accordance with Guidelines on EE&C Report issued by the Commission.
-
Conduct Energy Audit (EA) and Submit Energy Audit Report
Appoint a Registered Energy Auditor (REA) to conduct an energy audit and submit the energy audit report. The first audit report must be submitted within 1 year from the date of notice, and subsequent reports must be submitted every 5 years, or where an exemption notice is issued, in accordance with the period specified in the exemption notice. Report must be prepared in accordance with Guidelines on EA Report issued by the Commission.
Guidelines & Guides
The Energy Commission have developed 7 comprehensive guidelines and 3 detailed guides to support the Act and Regulations. These resources have been meticulously crafted to provide clear and actionable insights for various stakeholders. Summary for the guidelines and guides are as follows:
| DOCUMENT | TARGET | |||||
|---|---|---|---|---|---|---|
| Energy Consumer | Person in Charge of a Building | Manufacturer/ Importer | Energy Manager | Energy Auditor | Training Institution | |
| Guidelines on Ascertaining Energy Consumer | X | |||||
| Guidelines on Function and Duties of REM | X | X | ||||
| Guidelines on Energy Management System (EnMS) | X | X | ||||
| Guidelines on Energy Efficiency and Conservation Report | X | X | X | |||
| Guidelines on Ascertaining Building and Energy Intensity Performance of The Building | X | |||||
| Guidelines on Energy Audit Report | X | X | X | |||
| Guidelines on Energy Using Product | X | |||||
| Guide on Registration of Energy Manager | X | |||||
| Guide on Registration of Energy Auditor | X | |||||
| Guide on Registration of Training Institution | X | |||||
Information
Guidelines for New Enhanced Dispatch Arrangement
Guidelines for Solar Photovoltaic for Self-Consumption In Peninsular Malaysia (January 2025)