Clause 8.3: LCSP installed capacity shall not be less than 100kWp and not exceeding 2MWp per 11kV feeder, subject to the power system study, and have a Direct Connection to the Electricity Supply Network at low voltage.
a) How should Interconnection Solar be, at a Low Voltage Feeder Pillar or 11kV substation?
b) Is 2MW is accumulative at 11kV feeder or LV Feeder?

a) Solar output shall be directly connected to the Electricity Utility Company (EUC) and follow a similar connection like Feed-in-Tariff (FiT) to EUC LV grid i.e., solar connection before EUC supply meter.


b) LCSP installed capacity can be spread on different PE as long as it complies with the 2MWp cumulative per 11kV feeder.