CRESS
Similarly to the CGPP, will there be a commitment bond imposed on the RED?
No bond is required during CRESS submission. But Bank Guarantees will be required under:
i. NEDA CRESS Deed of Accession for the System Access Charge payment
ii. RESAA for Interconnection Facility works
CRESS
Are there any detailed guidelines on requirements to include community-scale battery storage?
What are the components in SAC?
Can lower System Access Charge (SAC) for Longer-Hour Batteries be considered?
What is the System Access Charge (SAC) for Non-Solar Technologies (e.g., Biomass/Biogas)?
What is excess energy?