For section 8.14 (a) of the CRESS Guidelines, can we understand that for a 100MWac plant, the usable other than nominal capacity for BESS shall be at least 50MW/200MWh?
Answer: Yes.
CRESS
Are there any detailed guidelines on requirements to include community-scale battery storage?
What are the components in SAC?
Can lower System Access Charge (SAC) for Longer-Hour Batteries be considered?
What is the System Access Charge (SAC) for Non-Solar Technologies (e.g., Biomass/Biogas)?
What is excess energy?