CRESS
If Power Plant type with FIRM output is submitted during application stage, does RED require to declare monthly energy output which will be subjected to excess energy clause? The energy storage capacity shall not be less than fifty percent (50%) of GEP r
Answer: Regardless of the plant type (Firm or non-firm output), the RED is required to declare the monthly energy output. This monthly energy output will be considered in the calculation of the excess energy in the event of withdrawal of a Green Consumer.
The registered capacity refers to the export capacity.
CRESS
Are there any detailed guidelines on requirements to include community-scale battery storage?
What are the components in SAC?
Can lower System Access Charge (SAC) for Longer-Hour Batteries be considered?
What is the System Access Charge (SAC) for Non-Solar Technologies (e.g., Biomass/Biogas)?
What is excess energy?