Preliminary check/study/PSS
Please advice if 132kV substation that is not in the list is allowed if preliminary check with PSS consultant shows that injection is feasible.
Participants are allowed to conduct Power System Study (PSS) for any nodal points that are not in the list provided by TNB Grid and TNB Retail. However, all costs associated to PSS shall be beared by participants as per Clause 8.8 of the Guide.
Please note that execution of PSS is not a guarantee for quota approval.