Preliminary check/study/PSS
Is Full PSS is required for NEDA? or PSS stage 1?
Yes, under NEDA, full PSS is required – Steady-state analysis, Transient analysis and Power Quality analysis.
Preliminary check/study/PSS
Please advice if 132kV substation that is not in the list is allowed if preliminary check with PSS consultant shows that injection is feasible.
If PSS rejected by TNB at NEDA stage, does it meant the CGPP application will be fully rejected?
Can interconnection solution be changed later if the PSS is not favourable?