Are there any limitations to the interconnection (export capacity) other than the PSS? i.e. Is the interconnection capacity set at 50% of the plant AC capacity?
Answer: The export capacity shall be as per PSS conducted capacity proposal. i.e., AC capacity.
CRESS
Are there any detailed guidelines on requirements to include community-scale battery storage?
What are the components in SAC?
Can lower System Access Charge (SAC) for Longer-Hour Batteries be considered?
What is the System Access Charge (SAC) for Non-Solar Technologies (e.g., Biomass/Biogas)?
What is excess energy?