How is wheeling availability is determined?

Answer: There are a few stages to determine the wheeling availability. At the planning stage, the PSS process will determine and advise if the chosen connection node is able to connect and safely evacuate RED (capacity in MW). This shall be the default wheeling availability.

However, operationally, GSO may advise on unavailability to wheel the energy due to grid system constraints- e.g., planned or forced outages or other emergency e.g., planned or unplanned transmission outages or any other system constraints that impact the wheeling availability.