If Power Plant type with FIRM output is submitted during application stage, does RED require to declare monthly energy output which will be subjected to excess energy clause? The energy storage capacity shall not be less than fifty percent (50%) of GEP r

Answer: Regardless of the plant type (Firm or non-firm output), the RED is required to declare the monthly energy output. This monthly energy output will be considered in the calculation of the excess energy in the event of withdrawal of a Green Consumer.

The registered capacity refers to the export capacity.