CRESS
If we declare the firm capacity for the next day, how long the plant need to maintain the firm capacity (i.e 6 hour, 12 hours etc?)
Please refer to the answer given in Q14 above.
CRESS
Are there any detailed guidelines on requirements to include community-scale battery storage?
What are the components in SAC?
Can lower System Access Charge (SAC) for Longer-Hour Batteries be considered?
What is the System Access Charge (SAC) for Non-Solar Technologies (e.g., Biomass/Biogas)?
What is excess energy?