CRESS

Referring to Section 13.4(g), the approved PSS is needed for the Submission Application, and Appendix 2 requires the Application to be submitted first before conducting PSS Studies. Can we assume that Section 13.4(g) refers to PSS Stage 1 and Appendix 2 r

i. Applicants must strictly adhere to the procedures outlined in the process flow chart provided in Appendix 2 of the Guidelines when submitting their CRESS applications.

ii. As stipulated in Section 13.2, the application must be submitted via the Single Buyer’s website at www.singlebuyer.com.my. Following submission, the applicant is required to undertake a Power System Study (PSS) to comply with the technical requirements of the CRESS application process.

iii. The scope of the PSS for each application shall encompass a comprehensive analysis, including steady-state and dynamic (transient) studies, as well as Reactive Power and Power Quality studies. These studies are mandated to ensure the proposed system's reliability and technical compliance.

iv. Upon completion of the PSS, applicants must secure approval for the study and submit the approval documentation as part of the CRESS application process.

v. It is imperative to note that the PSS study and its approval only address the technical requirements of the application. Applicants are reminded that all other requirements stipulated in the CRESS guidelines must also be fulfilled to achieve application completeness.